Question: 57


Teresa is able to see the Start Progress transition but not the Approve transition on an issue. Her co-worker is able to see both. Identify two possible causes why Teresa can NOT see the Approve transition. (Choose two.)

  1. Teresa is not listed in the correct security level for the issue.

  2. Teresa does not have the Transition Issues permission.

  3. Teresa is not in the correct group or project role.

  4. Teresa does not meet the condition on the Approve transition.

  5. Teresa does not have the correct global permission.

  6. Teresa does not have the correct Application access.


Answer: BC


Question: 58


Which two can project administrators associate with project roles? (Choose two.)

  1. Security levels

  2. Application access

  3. Global permissions

  4. Groups

  5. Individual users

  6. Project permissions


Answer: AD


Reference: https://confluence.atlassian.com/adminjiracloud/managing-project-roles-776636382.html

Question: 59


Martina is unable to perform the following actions in the App project: Create and manage versions

Create and manage components Rank issues in the backlog The App project does not use a shared permission scheme.

Which two permissions will allow her to perform those actions? (Choose two.)

  1. Transition Issues

  2. Move Issues

  3. Administer Projects

  4. Bulk Change

  5. Schedule Issues


Answer: CE


Reference: https://confluence.atlassian.com/adminjiracloud/managing-project-permissions-776636362.html

Question: 60


All projects use a shared permission scheme.

The Browse Projects permission needs to be updated. Project administrators need to be able to manage access to their own projects. What entry should be added to the Browse Projects permission?

  1. Group

  2. Project lead

  3. Project Role

  4. Single user

  5. Application access


Answer: B


Reference: https://confluence.atlassian.com/adminjiracloud/managing-project-permissions-776636362.html

Question: 61


Indicate which two use cases require the use of issue-level security within a project. (Choose two.)

  1. Only managers should be able to see Critical issues in the project.

  2. Only managers should be able to choose who sees certain issues in the project.

  3. Only managers should be able to see the project.

  4. Only managers should be able to set the Due Date on issues in the project.

  5. Only managers should be able to Close issues in the project.


Answer: BC


Reference: https://confluence.atlassian.com/adminjiracloud/configuring-issue-level-security-776636711.html

Question: 62


The extract of a permission scheme is shown below.

Clare is joining your team to help out as first-level support. Her job will be: Analyze incoming requests

Re-assign requests to subject matter experts

Which two project roles will she need? (Choose two.)

  1. Editors

  2. Workers

  3. Assigners

  4. Viewers

  5. Assignables

  6. Administrators


Answer: CD


Question: 63


The extract of a permission scheme is shown below

Angela is a new team member. Her main tasks are:

Which two project roles does she need? (Choose two.)

  1. Linkers

  2. Creators

  3. Editors

  4. Transitioners

  5. Viewers

  6. Administrators


Answer: AE


Question: 64


View the extract of a Jira Software Scrum project’s permission scheme shown.

The project uses a simplified workflow.

Who can drag and drop issues to the Closed column on the board?

  1. only the board administrator

  2. any user with Jira Software application access

  3. nobody

  4. any logged in user

  5. only members of the Administrators project role


Answer: B


Question: 65


For the DEV project, Max has these requirements relating to time logging: I need to be able to edit time logs.

I need to be able to delete time logs.

Which three project permissions does Max need in order to meet these requirements? (Choose three.)

  1. Schedule Issues

  2. Edit All Worklogs

  3. Move Issues

  4. Delete All Worklogs

  5. Work On Issues

  6. Edit All Comments


Answer: BDE