ACP-620 Dumps ACP-620 Braindumps

ACP-620 Real Questions ACP-620 Practice Test ACP-620 Actual Questions


killexams.com


Atlassian


ACP-620


Managing Jira Cloud Projects


https://killexams.com/pass4sure/exam-detail/ACP-620


Question: 44


Nash’s team just completed their first sprint.


What can they learn from this chart? (Choose three.)



Some of the issues are resolved during non-working days. of the issues are still unresolved.

sprint ends with 0 story points. sprint starts with 20 story points.

are issues worth 5 story points resolved on July 13th. are no scope changes in this sprint.

(Assume Remaining Estimate and Time Spent is enabled for this board.)


A.

  1. Some

  2. This

  3. This

  4. There

  5. There


Answer: C,E,F Explanation:

The grey area indicates non-working days. There were no issues resolved during non-working days since story points did not reduce in the grey area.


This chart starts drawing the Guideline and Remaining Values lines at the 18 story points on the y-axis.

On July 13th, story points were reduced from 15 to 10. This means that users have closed some issues that are worth 5 story points.


Users have closed all issues on July 20th. There are no story points remaining on this date.


Story points do not increase during this sprint. Since the Remaining Estimate and Time Spent is enabled for this board, scope change is indicated in the Burndown Chart for the subtask.


Question: 45


A group of developers are working on multiple Jira projects. They can view all Jira projects and have the ‘Move Issues’ permission in all Jira projects. However, they cannot move issues to some of the Jira projects.


the possible root cause of this problem?

do not have the ‘View Issue’ permission in some projects.

do not have the ‘Transition Issue’ permission in some projects. do not have the ‘Edit Issue’ permission in some projects.

do not have the ‘Create Issue’ permission in some projects.


r: D ation:

are moving issues from project to project, they need to make sure they have the Create Issues permissi project they want to move it to.


on: 46


cently joined the team as a scrum master.


ermission will allow Nash to perform the below actions? (Choose four.) ge version

ge component ge sprint

n issue’s due date minister Projects

What is

  1. They

  2. They

  3. They

  4. They


Answe


Explan


If users on in

the Jira


Questi Nash re Which p


Question: 48

Nash is creating a new Scrum board with multiple Jira projects. Each project has a different status in its workflow. Which of the following are true? (Choose two.)

  1. Some issues will be hidden from the board.

  2. The user cannot create a new board with multiple Jira projects.

  3. All statuses will be mapped to 3 default columns: To Do, In Progress, and Done

  4. All issues will be hidden from thewwwboard.dumpspanda..com

  5. The status will be mapped to the first selected project when creating the new board.


Answer: C,D Explanation:

If users are creating a new board (Kanban or Scrum) with multiple Jira projects, and each project has a unique workflow, all statuses will be mapped to 3 default columns: To Do, In Progress, and Done.


anban board, the issues will appear on the board as soon as users create the board.


crum board, all issues will not appear on the board because only issues in the active sprint will appear oard. After creating a new Scrum board, you do not have an active sprint.


on: 49


f the following are false about the roadmap? (Choose three.)

Users can choose which epics they want to display on the dashboard. Either Complete or Incomplete.

can change the view setting to customize their roadmap’s view. The changes will apply to all users tha o that project.

edule bars for child issues are currently available for scrum teams only. Users can customize epic’s color directly from the roadmap.

can change the epic bar timeline to weeks, months, quarters, or yearly.


r: A,B,E


ation:


ettings is a collection of settings that allow users to adjust their personal view of the roadmap. The setti individual users. Users can change their view at any time.


le Bars for child issues are currently available for scrum teams only.


isplay Options allow users to use the dropdown to select which epics to display. The current options are lete, or Complete.

On the K


On the S on the

Scrum b


Questi


Which o A.

  1. Users t have

    access t

  2. Sch D.

E. Users


Answe


Explan


View S ngs only

apply to


Schedu


Epic D All,

Incomp

Users can adjust the color of an epic directly on the roadmap. Simply right-click the epic and choose a fresh color. The epic bar has a default duration according to how users view their timeline. The default durations are weeks,

months, or quarters.


Question: 50


Which of the following can be explained from the chart below?



Users have not started the sprint yet. deleted the sprint.

closed some issues the moment the sprint started. There are no issues in the sprint.


r: C ation:

rey ‘guideline’ line does not show, the sprint may have been started before any issues were assigned to


ase, since the grey ‘guideline’ line does show up in the chart, the sprint already started. The ‘remaining icates that someone closed some issues that are worth 5 story points as soon as they started their sprint.

A.

  1. Users

  2. Users D.


Answe


Explan


If the g it.


In this c values’

line ind