Question: 108


The event may be

A . Singular or multiple B . Certain or uncertain C . Loss or gain

D . Negative or positive


Answer: A


Question: 109


The data validation step stresses the need for a knowledgeable individual.

A . To comparing data from the inspections to the expected deterioration mechanism and rates B . To compare the results with previous measurements on that system

C . Similar systems at the site or within the company or published data D . All of the above


Answer: D


Question: 110


Rbi is focused on a systematic determination of A . Relative risks

B . Absolute risks

C . Comparable risks D . Total risks


Answer: A


Question: 111


to be established to judge acceptability of risk couldhe an objective of the rbi assessment if such criteria do not exist already within the user’s company.

A . Risk criteria B . Risk plan

C . Risk analysis


Answer: A


Question: 112


The primary work products of the rbi assessment and management approach and implementation of rbi provides A . Overall reduction of risk and acceptance of current risk

B . Overall increase of risk and acceptance of risk

C . Overall reduction of risk and negligence of current risk

D . Overall increase of risk and negligence of current risk


Answer: A


Question: 113


Who can provide useful input (such as the spectrum of process conditions, injection points etc.) To aid materials specialists in the identification of deterioration mechanisms and rates

A . Process specialists

B . Plant operation specialists C . Asset integrity experts

D . Inspection engineers


Answer: A


Question: 114


Following are some of the recognized risks which cannot be managed by inspection alone except one A . Equipment nearing retirement

B . Failure mechanisms (such as brittle fracture, fatigue) where avoidance of failure primarily depends on operating within a defined pressure/temperature envelope

C . Consequence-dominated risks

D . The suitability and current condition of the equipment within the current operating envelope will determine the probability of failure (pof) of the equipment from one or more deterioration mechanisms


Answer: D


Question: 115


The models are evaluated to provide both qualitative and quantitative insights about the level of risk and to identify the design, site, or operational characteristics that are the most important to risk

A . Probabilistically B . Statistically

C . Linearly D . Logically


Answer: D


Question: 116


The primary audience for rp 580 is

A . Inspection and materials engineering personnel B . Maintenance personnel

C . Only inspection personnel

D . Only materials engineering personnel

Answer: C


Question: 117


If the probability and consequence combination (risk) is high enough to be unacceptable, then A . A mitigation action to predict or prevent the eventis recommended.

B . A mitigation action to predict or prevent the event isnot recommended C . Warrant to analyze risks involved


Answer: A


Question: 118


A process to assess risks, to determine if risk reduction is required and to develop a plan to maintain risks at an acceptable level

A . Risk management B . Risk mitigation

C . Risk control


Answer: A


Question: 119


The amount and type of codes and standards used by a facility can have A . Significant impact on rbi results

B . No impact on rbi results

C . Less significant impact on rbi results


Answer: A


Question: 120


Thing or activity with a potential for con- sequence A . Source

B . Hazard C . Toxic


Answer: A