Question: 15


What is an epic?


  1. A low-level requirement

  2. A fine-grained user story

  3. A detailed feature

  4. A high-level requirement


Answer: D


Explanation:


Reference: https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_160&showNav=t rue&expandNav=true


Question: 16


Which process can take place during a release review workshop?


  1. Controlling a stage

  2. Managing product delivery

  3. Managing a stage boundary

  4. Directing a project Answer: B Question: 17

Which statement about the âprotect the level of qualityâ target is CORRECT?


  1. It is achieved by allowing enough time for testing

  2. It is achieved by using the same team members

  3. It gives confidence on the progress of the project

  4. It delivers the early realization of benefits


Answer: D


Explanation:


Reference: https://publications.axelos.com/prince2agile2016/content.aspx? showNav=true&expandNav=true&page=PRA_41#:~:text=PRINCE2%20Agile%20protects%20the%20level,the%20quality%20level%20is%20met


Question: 18


Which is often used during a retrospective to capture lessons?


  1. A Glad! Sad! Mad! board

  2. A Kanban board

  3. A burn chart

  4. A Gantt chart Answer: A Explanation:

Reference: https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_120&showNav=t rue&expandNav=true

Question: 19


Which statement explains how the âlearn from experienceâ principle is applied in an agile context?


  1. It focuses on the prioritization and decomposition of requirements

  2. It integrates releases within management stages

  3. It is supported by the âinspect and adaptâ concept

  4. It provides guidance on mapping PRINCE2 roles to an agile environment


Answer: C


Explanation:


Reference: https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_46


Question: 20


How does agile address the risk associated with the project not being fully understood at the beginning?


  1. By allowing a lot of detail at the start

  2. By avoiding too much detail at the start

  3. By requiring details at the start

  4. By preventing the analysis of details at the start


Answer: D Question: 21

What should be emphasized when tailoring the PRINCE2 Progress theme?


  1. Monitoring what is being delivered

  2. Tracking time and cost

  3. Planning resources

  4. Assessing the impact of risks


Answer: A Question: 22

In Scrum, what answers the question âwhat can be done this sprint?â


  1. Daily scrum

  2. Sprint review

  3. Sprint planning

  4. Increment Answer: A Question: 23

What needs to happen when new detailed requirements are added to a timebox?


  1. Requirements of a similar level of effort should be removed

  2. More people should be added to the delivery team

  3. The delivery milestones should be reviewed and re-planned

  4. Formal change control should be applied


Answer: A Question: 24

What term is used to describe boards that display what work needs to be completed for people working on a project?


  1. Work in progress limit

  2. Information radiator

  3. Highlight report

  4. Glad! Sad! Mad! Answer: C Explanation:

Reference: https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_190&showNav=t rue&expandNav=true


Question: 25


In which area is Agile strongest when blending with PRINCE2?


  1. Product delivery

  2. Project management

  3. Project direction

  4. Product management Answer: A Explanation:

Reference: https://hennyportman.wordpress.com/2015/07/01/prince2-agile-in-one-

picture/#:~:text=This%20framework%20is%20based%20on,the%20area%20of%20product %20delivery


Question: 26


Which statement about the waterfall methodology definition is CORRECT?


  1. It states that deadlines should not be moved

  2. It has distinct goals for each stage of development

  3. It is a behavior that involves making things transparent

  4. It promotes the use of experiments carried out in a scientific way


Answer: B


Explanation:


Reference: https://www.lucidchart.com/blog/agile-vs-waterfall-vs-kanban-vs-scrum


Question: 27


How is the âtailor to suit the projectâ principle applied in an agile context?


  1. By flexing what is produced to stay in control and deliver value

  2. By emphasizing tolerances on what is being delivered

  3. By using the Agilometer to assess the project environment

  4. By fitting releases into planned management stages


Answer: A Question: 28

Which statement about quality tolerances for a product is CORRECT in an agile context?

  1. All quality criteria tolerance must be fixed

  2. Quality tolerances should be the same for all quality criteria

  3. Setting quality tolerance relies on prioritising quality criteria

  4. All quality criteria should have zero tolerance


Answer: C Question: 29

Which statement about the âprotect the level of qualityâ target is CORRECT?


  1. It is achieved by ensuring that all features are delivered

  2. It is unlikely to be achieved if incomplete user documentation is provided

  3. It allows change at the detailed level to be handled dynamically

  4. It avoids the use of extra people to improve progress during a timebox


Answer: A Question: 30

Which statement explains the target âbe on time and hit deadlinesâ for flexible delivery?


  1. It reduces testing in order to meet deadlines

  2. It sets the project baseline at the correct level

  3. It enables team dynamics to remain the same

  4. It improves the supplier's reputation with the customer


Answer: A


Explanation:


Reference: https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_41