Question #274 Section 6
A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?
8
18
36
40
https://www.izenbridge.com/blog/how-to-calculate-communication-channels/
Question #275 Section 6
A project conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type communication is this?
Informal
Unofficial
Formal
Hierarchical
https://yodiz.com/help/agile-scrum-meetings/
Question #276 Section 6
Which of the following are processes associated with Project Cost Management?
Develop Costs, Estimate Costs, Determine Budget, Control Costs
Develop Budget, Determine Budget, Determine Risks, Control Costs
Plan Cost Management, Estimate Costs, Determine Budget, Control Costs
Plan Budget Management, Determine Budget, Create Cost Accounts, Control Costs
https://blog.masterofproject.com/cost-management/
Question #277 Section 6
A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated.
Which estimation method did the team use?
Rolling wave planning
Expert judgment
Decomposition
Data analysis
Question #278 Section 6
A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?
Project level
Organizational level
Industry level
Influential level
Question #279 Section 6
A project had four phases, and at the end of the third phase, the project manager realized that some of the project execution steps could have been improved to avoid team burn out
What should the project manager have done differently?
Conduct performance reviews
Review quality reports with the project team
Hold regular meetings with the project team
Conduct a retrospective session at the end of each phase
Question #280 Section 6
A project manager is in the process of working with stakeholders to meet their needs and expectations, and identifying and fostering communication and involvement. Which process does this typically represent?
Monitor Stakeholder Engagement
Monitor Communications
Manage Communications
Manage Stakeholder Engagement
https://www.memrise.com/course/352178/pmbok-5-project-management-exam-study/52/
Question #281 Section 6
Stakeholder identification and engagement should begin during what phrase of the project?
After the project management is completed
After the stakeholder engagement plan is completed
As soon as the project charter has been approved
After the communications management plan is completed
https://pmstudycircle.com/2012/06/identify-stakeholders-project-management/
Question #282 Section 6
What type of risk is Variability risk?
Emerging risk
Non-event risk
Ambiguity risk
Integrated risk
Question #283 Section 6
A project manager is talking with their manager about the advantages of following a particular project management approach. What component of the project manager's sphere of influence does this represent?
The project
The organization
Professional discipline
Across disciplines
Question #284 Section 6
What is the main benefit of the lessons learned register?
Provides validation requirements
Supplies monitoring and reporting methods
Improves the performance of future projects
Documents the status of deliverables and project results
Question #285 Section 6
What major skill sets comprise the PMI Talent Triangle?
Technical project management, technology management, and strategic and business management
Technical project management, leadership, and strategic and business management
Leadership, operational management, and technical project management
Organizational management, operational management, and technology management
https://www.pmi.org/learning/training-development/talent-triangle#:~:text=The%20ideal%20skill%20set%20%E2%80%94%20the,%E2%80%94% 20and%20now%2C%20digital%20skills
.
Question #286 Section 6
What tool or technique will establish expected behaviors for project team members?
Ground rules
Decision making
Power/influence grid
Stakeholder engagement assessment matrix