image


CCE-CCC Dumps CCE-CCC Braindumps

CCE-CCC Real Questions CCE-CCC Practice Test CCE-CCC Actual Questions


PMI


CCE-CCC


Certified Cost Consultant / Cost Engineer (AACE International)


https://killexams.com/pass4sure/exam-detail/CCE-CCC


:


QUESTION 87

image


The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4? A. $1890/ton

  1. $1863/ton

  2. $1948/ton D. $1836/ton


Answer: D


:


QUESTION 88

AACE International defines as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.


  1. Risk analysis

  2. Benefit/Cost ratio (B/C) method

  3. Net present worth method

  4. Life cycle costs method (LCC)


Answer: D


:


QUESTION 89

can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.


  1. Economic optimization

  2. Simulation

  3. Linear programming

  4. Dynamic programming


Answer: D


:


QUESTION 90

What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?


  1. Liability insurance

  2. Performance bond

  3. Bid bond

  4. Surety bond


Answer: B


:


QUESTION 91

Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and skill levels. What does this scenario describe?


  1. Productivity efficiency factor

  2. Value engineering

  3. Cash flow

  4. The learning curve


Answer: D


:


QUESTION 92

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Which of the following methods a used for creating critical path schedules:


  1. Precedence diagram method

  2. Precedence and arrow diagram methods only

  3. Gantt chart (bar chart) method

  4. Arrow diagram method


Answer: B


A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.


You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week. According to your calculations, the project has a schedule performance index of 0.80. What would you advise the management about the scheduled completion date?


  1. Project will be completed in 20 more weeks

  2. Project will be completed this week - on schedule

  3. Project will be completed in 4 more weeks

  4. Project will be completed in 12.8 more weeks


Answer: C


:


QUESTION 94

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.


The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?


  1. Recalculate the early finish for each activity

  2. Recalculate the early start for each activity

  3. Update the remaining duration for each activity

  4. Recalculate the critical path


Answer: D


A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.


The recognition of loss of value of a natural resource used in the production process is referred to as:


  1. Capital reduction

  2. Net loss

  3. Depreciation

  4. Depletion


Answer: D


:


image

6$03/( 48(67,216


7KHVH TXHVWLRQV DUH IRU GHPR SXUSRVH RQO\ )XOO YHUVLRQ LV XS WR GDWH DQG FRQWDLQV DFWXDO TXHVWLRQV DQG DQVZHUV


.LOOH[DPV FRP LV DQ RQOLQH SODWIRUP WKDW RIIHUV D ZLGH UDQJH RI VHUYLFHV UHODWHG WR FHUWLILFDWLRQ H[DP SUHSDUDWLRQ 7KH SODWIRUP SURYLGHV DFWXDO TXHVWLRQV H[DP GXPSV DQG SUDFWLFH WHVWV WR KHOS LQGLYLGXDOV SUHSDUH IRU YDULRXV FHUWLILFDWLRQ H[DPV ZLWK FRQILGHQFH +HUH DUH VRPH NH\ IHDWXUHV DQG VHUYLFHV RIIHUHG E\ .LOOH[DPV FRP


$FWXDO ([DP 4XHVWLRQV .LOOH[DPV FRP SURYLGHV DFWXDO H[DP TXHVWLRQV WKDW DUH H[SHULHQFHG LQ WHVW FHQWHUV 7KHVH TXHVWLRQV DUH XSGDWHG UHJXODUO\ WR HQVXUH WKH\ DUH XS WR GDWH DQG UHOHYDQW WR WKH ODWHVW H[DP V\OODEXV %\ VWXG\LQJ WKHVH DFWXDO TXHVWLRQV FDQGLGDWHV FDQ IDPLOLDUL]H WKHPVHOYHV ZLWK WKH FRQWHQW DQG IRUPDW RI WKH UHDO H[DP


([DP 'XPSV .LOOH[DPV FRP RIIHUV H[DP GXPSV LQ 3') IRUPDW 7KHVH GXPSV FRQWDLQ D FRPSUHKHQVLYH FROOHFWLRQ RI TXHVWLRQV DQG DQVZHUV WKDW FRYHU WKH H[DP WRSLFV %\ XVLQJ WKHVH GXPSV FDQGLGDWHV FDQ HQKDQFH WKHLU NQRZOHGJH DQG LPSURYH WKHLU FKDQFHV RI VXFFHVV LQ WKH FHUWLILFDWLRQ H[DP


3UDFWLFH 7HVWV .LOOH[DPV FRP SURYLGHV SUDFWLFH WHVWV WKURXJK WKHLU GHVNWRS 9&( H[DP VLPXODWRU DQG RQOLQH WHVW HQJLQH 7KHVH SUDFWLFH WHVWV VLPXODWH WKH UHDO H[DP HQYLURQPHQW DQG KHOS FDQGLGDWHV DVVHVV WKHLU UHDGLQHVV IRU WKH DFWXDO H[DP 7KH SUDFWLFH WHVWV FRYHU D ZLGH UDQJH RI TXHVWLRQV DQG HQDEOH FDQGLGDWHV WR LGHQWLI\ WKHLU VWUHQJWKV DQG ZHDNQHVVHV


*XDUDQWHHG 6XFFHVV .LOOH[DPV FRP RIIHUV D VXFFHVV JXDUDQWHH ZLWK WKHLU H[DP GXPSV 7KH\ FODLP WKDW E\ XVLQJ WKHLU PDWHULDOV FDQGLGDWHV ZLOO SDVV WKHLU H[DPV RQ WKH ILUVW DWWHPSW RU WKH\ ZLOO UHIXQG WKH SXUFKDVH SULFH 7KLV JXDUDQWHH SURYLGHV DVVXUDQFH DQG FRQILGHQFH WR LQGLYLGXDOV SUHSDULQJ IRU FHUWLILFDWLRQ H[DPV


8SGDWHG &RQWHQW .LOOH[DPV FRP UHJXODUO\ XSGDWHV LWV TXHVWLRQ EDQN DQG H[DP GXPSV WR HQVXUH WKDW WKH\ DUH FXUUHQW DQG UHIOHFW WKH ODWHVW FKDQJHV LQ WKH H[DP V\OODEXV 7KLV KHOSV FDQGLGDWHV VWD\ XS WR GDWH ZLWK WKH H[DP FRQWHQW DQG LQFUHDVHV WKHLU FKDQFHV RI VXFFHVV


7HFKQLFDO 6XSSRUW .LOOH[DPV FRP SURYLGHV IUHH [ WHFKQLFDO VXSSRUW WR DVVLVW FDQGLGDWHV ZLWK DQ\ TXHULHV RU LVVXHV WKH\ PD\ HQFRXQWHU ZKLOH XVLQJ WKHLU VHUYLFHV 7KHLU FHUWLILHG H[SHUWV DUH DYDLODEOH WR SURYLGH JXLGDQFH DQG KHOS FDQGLGDWHV WKURXJKRXW WKHLU H[DP SUHSDUDWLRQ MRXUQH\


'PS .PSF FYBNT WJTJU IUUQT LJMMFYBNT DPN WFOEPST FYBN MJTU

.LOO \RXU H[DP DW )LUVW $WWHPSW *XDUDQWHHG