Certified Cost Consultant / Cost Engineer (AACE International)
https://killexams.com/pass4sure/exam-detail/CCE-CCC
:
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4? A. $1890/ton
$1863/ton
$1948/ton D. $1836/ton
:
AACE International defines as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.
Risk analysis
Benefit/Cost ratio (B/C) method
Net present worth method
Life cycle costs method (LCC)
:
can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.
Economic optimization
Simulation
Linear programming
Dynamic programming
:
What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?
Liability insurance
Performance bond
Bid bond
Surety bond
:
Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and skill levels. What does this scenario describe?
Productivity efficiency factor
Value engineering
Cash flow
The learning curve
:
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Which of the following methods a used for creating critical path schedules:
Precedence diagram method
Precedence and arrow diagram methods only
Gantt chart (bar chart) method
Arrow diagram method
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week. According to your calculations, the project has a schedule performance index of 0.80. What would you advise the management about the scheduled completion date?
Project will be completed in 20 more weeks
Project will be completed this week - on schedule
Project will be completed in 4 more weeks
Project will be completed in 12.8 more weeks
:
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?
Recalculate the early finish for each activity
Recalculate the early start for each activity
Update the remaining duration for each activity
Recalculate the critical path
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The recognition of loss of value of a natural resource used in the production process is referred to as:
Capital reduction
Net loss
Depreciation
Depletion
: