  1. master file

  2. product structure file

  3. routing file

  4. All of the above




Answer: D



Question: 574

Which file contains a list of the single-level components and quantities needed to

assemble a parent?


  1. master file

  2. product structure file

  3. routing file

  4. work center master file




Answer: B



Question: 575

What consist of a series of operations required to make the item?


  1. routing

  2. builds

  3. procedures

  4. All of the above




Answer: A



Question: 576

Each active manufacturing order has a record in which file?


  1. work center master file

  2. work center detail file

  3. shop order master file

  4. shop order detail file




Answer: C



Question: 577

The time normally required to produce an item in a typical lot quantity is known as:


  1. Manufacturing load time

  2. Manufacturing conduct time

  3. Manufacturing control time

  4. Manufacturing lead time




Answer: D



Question: 578

Which of the following is NOT the manufacturing lead time?


  1. Queue time

  2. Setup time

  3. Run time

  4. Load time




Answer: D



Question: 579

What must manage both the input of orders to the production process and the availability

capacity to control queue and work-in process?


  1. Run time activity

  2. Production activity control

  3. Activity management

  4. Work center manufacturing activity




Answer: B



Question: 580

The length of time from when material enters a production facility until it exists, this is

known as:


  1. throughput time

  2. workforce time

  3. creation time

  4. assembly time




Answer: A



Question: 581

What is used to calculate how long it will take to complete a task?


  1. Forward scheduling

  2. Finite scheduling

  3. Self-assured scheduling

  4. Bold scheduling




Answer: A



Question: 582

When the last operation is on the routing is scheduled first and is scheduled for complete at the due date, this is called:


  1. Timid scheduling

  2. Rearward scheduling

  3. Self-assistant scheduling

  4. Backward scheduling




Answer: D



Question: 583

Backward scheduling is used to determine when an order must be started.


  1. True

  2. False




Answer: A



Question: 584

If the run time per piece on operation B is shorter than that on A, the first batch must be

larger enough to avoid idle time on operation A.


  1. True

  2. False




Answer: B



Question: 585

Operational splitting is practical when:


  1. setup time is low compared to run time

  2. a suitable work center is idle

  3. it is possible for an operator to run more than one machine at a time

  4. All of the above




Answer: D



Question: 586

The time needed to unload and load must be shorter than .


  1. run time per piece

  2. planning time

  3. manufacturing time

  4. resource utilization time




Answer: A



Question: 587

A facility, function, department, or resource whose capacity is equal to or less than the

demand placed upon it is known as:


  1. timeframe

  2. bottleneck

  3. elapsed operation

  4. none of the above




Answer: B



Question: 588

The operation that controls the work feeding the bottleneck and must operate at a rate

equal to the output of the bottleneck so the time buffer queue is maintained is known as:


  1. gateway operation

  2. bottleneck operation

  3. task operation

  4. Control buffer operation




Answer: A