Question: 101


The advantage of the Earned Value approach is that it allows the early detection of slippage by using an industry standard approach to:

  1. Measure a project’s actual progress

  2. Forecast both project completion date and final cost

  3. Track schedule and budget throughput the project life cycle

  4. All of the above

  5. None of the above




Answer: D



Question: 102


Quality Requirements are generally:

  1. Analogue (a range of acceptable values)

  2. Binary (on or off, present or not)

  3. Either Analogue or Binary

  4. None of the above




Answer: A



Question: 103


Which of the following is the best tools for planning, tracking, and reporting time related activities?

  1. Gantt Charts

  2. Control Charts

  3. Histogram

  4. Run Chart




Answer: C



Question: 104


The External Design Process determines:

  1. What are the major components of a product

  2. What will happen within each of the major components

  3. Provides a map of the sub-components

  4. Individual items of sub component




Answer: A



Question: 105


Which of the following represent the components of a data flow diagram?

  1. External entities, processes, data stores, data flow

  2. Name, aliases, entities, process flow, sequences

  3. Concept, attributes, relationships, metadata

  4. Entities, attributes, processes, data stores, data flow




Answer: A



Question: 106


The State Transition Diagram:

  1. Represents all states in which an object may exist

  2. Depicts functions that transforms the data flow

  3. Indicates how data are transformed by the system

  4. Indicates how system reacts to external events




Answer: A



Question: 107


Critical Assumptions are key factors for the project that are:

  1. Outside the control of the project team

  2. Within the control of the project team

  3. Irrelevant whether the project team controls them or not




Answer: A



Question: 108


Entity Relationship Diagrams identify:

  1. Trace the movement of information through a process

  2. How and when transformations occur

  3. Define all of the components of a specific activity

  4. Who and what are involved in a process and how they interact




Answer: D



Question: 109


Which of the following techniques was developed by Drs. Robert Kaplan and David Norton?

  1. Enterprise Dashboard

  2. Business Dashboard

  3. PDCA

  4. Balanced Scorecard




Answer: D



Question: 110


Creating a baseline of current performance is part of planning phase.

  1. True

  2. False




Answer: A



Question: 111


Guidelines are not enforceable.

  1. True

  2. False




Answer: A



Question: 112


Interoperability is the:

  1. Effort required to enhance and improve the product

  2. Extent to which the system is capable of being used in multiple applications

  3. Extent to which a program can be used in other applications

  4. Effort required to couple and uncouple systems




Answer: D