Exam Code : CTAL-TTA-001
Exam Name : ISTQB Certified Tester Advanced Level - Technical Test Analyst (CTAL-TTA-Syll2012)
Vendor Name :
"iSQI"
CTAL-TTA-001 Dumps
CTAL-TTA-001 Braindumps CTAL-TTA-001 Real Questions CTAL-TTA-001 Practice Test CTAL-TTA-001 Actual Questions
killexams.com
ISTQB Certified Tester Advanced Level - Technical Test Analyst (CTAL-TTA-Syll2012)
https://killexams.com/pass4sure/exam-detail/CTAL-TTA-001
A design review meeting
An architect translating requirements into design
Performing unit tests against design
A test log showing code coverage achieved
Part 7 "Test Process & Incident Management"
As a technical test analyst, which documents would you typically create? 1 credit [K2]
Test plan, test design, test cases and test log
Test plan, test log, test design and test summary report
Test script, test log, incident report and test design
Incident report, test item transmittal report, test cases and test procedure
Part 7 "Test Process & Incident Management"
As a technical test analyst, you have found out during test case design that the design document is incomplete. Which is an example of a good way to communicate that problem in an email? 1 credit [K2]
E-mail: “Until I have received an updated version of the design document, I will not do any work on the test design.”
E-mail: “When will it be possible to receive the missing information? Test design is impeded by a lack of clarity here.”
E-mail: “Here we go again. The developer gave us incomplete and ambiguous design specifications. Typical.”
Do not communicate the problem, just log the delaying effect of the information problem and be ready to explain the delays to the test manager later.
Part 7 "Test Process & Incident Management"
As a technical test analyst, you are involved in a risk analysis session using the Failure Mode and Effect Analysis technique. You are calculating risk priorities. Which of the following are the major factors in this exercise? 1 credit [K2]
Severity and priority
Functionality, reliability, usability, maintainability, efficiency and portability
Likelihood and impact
Financial damage, frequency of use and external visibility
Part 7 "Test Process & Incident Management"
In which of the following test documents would you expect to find the preconditions to start executing a set of test cases? 1 credit [K2]
Level test plan
Test procedure specification
Test design specification
Master test plan
Part 7 "Test Process & Incident Management"
Defects are discovered through test analysis and design because… 1 credit [K2]
the tasks involve extracting information from the test basis
developers are involved in writing test cases
the cost of fixing a defect will increase if found later on
the author of the test basis will have made errors
Part 7 "Test Process & Incident Management"
The development manager asks you to identify suitable test coverage entry criteria for a component test. Which TWO of the following would you recommend as appropriate for entry criteria to a component testing phase? 2 credits [K3]
100% statement coverage
No critical outstanding defects
Test log available
Code review completed
Static analysis shows no major violations
Identify the most significant risk introduced by this approach to incident management. 3 credits [K4]
Excel list may not be insynchronizationwith Word documents
Low level of usability
Spreadsheet/text files may not be complete
Does not map to IEEE 1044