Question: 45


Refer to the exhibit.


A customer needs a wired network upgrade and has complained about performance issues. The architect has collected information about traffic flow on several switch ports in different locations across the network, and the results are shown in the exhibit. Each of these ports is a 1Gbps port. What can the architect conclude?

  1. None of these ports show any periods of congestion.

  2. Port 1 shows periods of congestion, other ports are not congested.

  3. Port 3 shows periods of congestion, other ports are not congested.

  4. All of the ports show serious congestion.




Answer: D



Question: 46


What is one reason to deploy an Aruba 8320 switch when compared to an Aruba 5400R switch?

  1. to support cloud-based management and guest services through Aruba Central integration

  2. to obtain a great number of options for types of ports, including PoE and non-PoE

  3. to enhance network monitoring and analytics

  4. to support Zero Touch Provisioning (ZTP)




Answer: C



Question: 47


A hospital needs a wireless solution which will provide guest access for patients and visitors, as well as for medical staff. In addition to laptops and tablets, staff have wireless voice communicator devices. Some medical equipment also connects wirelessly.

How can the network architect help to ensure that patient and visitor internet use does not interfere with more vital hospital applications?

  1. Deploy IntroSpect to monitor patient and visitor traffic.

  2. Plan a bandwidth contract for the guest role in the MC firewall.

  3. Deploy dedicated Air Monitors (AMs) at about one-fourth the density of APs.

  4. Ensure that the guest SSID has a password associated with it.



Answer: C



Question: 48


Refer to the exhibit.

A mall has an existing Aruba solution with 15 AP-335s. The mall now wants to add Meridian and location-based services, in particular blue dot wayfinding. The customer plans to use the built-in beacon in the existing AP radios. These Meridian licenses have been proposed:

1x Aruba Meridian Maps

1x Aruba Meridian Blue Dot Nav

Which concern should the architect raise about this plan?

  1. Separate beacons should be deployed to provide proper coverage for wayfinding.

  2. Only the Blue Dot Nav license is required to meet the customer requirements.

  3. The customer requires wireless sensors to manage the beacons in the AP radios.

  4. The existing AP radios do not support beacon functionality.




Answer: A



Question: 49


Refer to the exhibit.

A customer needs a wired upgrade for a building on its main campus. The exhibit shows the switches that architect has selected for each closet and the existing cabling. The customer is not open to changing the cabling.

The customer requires link redundancy for the uplinks from each closet and for the links from the building to the core. In non link failure situations, the uplinks from each closet must support at least 20 Gbps, and the building as a whole must have at least 20 Gbps to the core in non link failure situations.

Which options for connecting the closets to the network core are valid? (Select two.)

  1. Connect the switch stack on each floor directly to the network core on two fiber connections per floor. Achieve this by patching the inter-floor fiber through the inter-building fiber.

  2. Add two aggregation switches in the Floor 1 closet. Connect the switch stack for each closet to the aggregation switches on two fiber links each and the aggregation switches to the core on two fiber links.

  3. Combine the nine switches on all three floors into a single switch stack with stacking cables in a ring topology. Connect two Floor 1 members to the network core with one fiber connection each.

  4. Combine the nine switches on all three floors into a single switch stack with the MM OM3 fiber cables in a ring topology. Connect two Floor 1 members to the network core with one fiber connection each.

  5. Connect the Floor 2 switch stack to Floor 1 with two fiber connections. Do the same for Floor 3. Connect the Floor 1 switch stack to the network core with two fiber connections.



Answer: BC



Question: 50


A customer has phones used as wireless Voice over IP (VoIP) devices. Which is one implication for the design?

  1. Plan policies for the phone role on MCs to give the phones a high QoS priority.

  2. Ensure a -75 GHz signal in both the 2.4GHz band and the 5GHz band across the entire site.

  3. Ensure that APs connect on Smart Rate ports to support the high bandwidth demands of the phones.

  4. Apply a bandwidth contract to the phone VLAN to limit broadcast and multicast traffic.




Answer: C



Question: 51


Refer to the exhibit.

A casino and a retail space has an existing Aruba network with Aruba AP-335s. The customer wants to deploy Meridian and enable proximity-based campaigns. The exhibit shows a segment of the

floor plan. When visitors enter the areas circled in the exhibit, they should receive a targeted notification about promotions and sales. What should the architect explain to the customer about how to finish the solution?

  1. This solution will require about 6 battery-powered beacons, which can be managed by the APs.

  2. While these APs cannot act as beacons, they have a USB slot that accepts USB beacons.

  3. The customer can enable the built-in BLE capability in the AP-335 radio to meet these requirements.

  4. The customer must remember to purchase a Meridian Maps license with the Campaigns license.




Answer: A



Question: 52


Refer to the exhibit.


A hotel needs a wireless solution. The architect has selected 303H Series, controlled by a local MC, as the best choice. The hotel plans to have the APs installed in the existing wall boxes which have one Ethernet port each. The architect has created to BOM shown in the exhibit. (Note that this portion of the BOM does not include the MC, which is not part of this question.) Which additional

clarification should the architect seek to determine whether this BOM fully meets the customer needs?

  1. whether the hotel wants to deploy the APs as RAPs or CAPs

  2. whether the hotel has CAT5e patch cables long enough to reach the boxes

  3. whether directional or omnidirectional external antennas work better for the APs

  4. whether the hotel already has a PoE or PoE+ source




Answer: D



Question: 53


A hospital needs an upgrade to 802.11ac for its wireless network. The wireless network supports:


All of these devices support both the 2.4GHz and 5GHz band. Assuming about a max throughput of 150 Mbps per AP, the hospital would like to support about 4 Mbps per client.

The architect has used VisualRF to plan the AP placement on one of the floors, which the hospital expects will need to support about 800 wireless devices. The exhibits show heatmaps from this plan. The architect also plans to deploy APs in stairwells between floors.

How well does the plan meet the requirements?

  1. The current AP placement fails to account for the lead-lined walls that are common in patient and exam rooms.

  2. The current AP placement fails to provide adequate signal for the voice communicators in several areas.

  3. The current AP placement meets coverage requirements, but does not meet capacity requirements.

  4. The current AP placement meets the customer requirements in terms of coverage and capacity.




Answer: D



Question: 54


An indoor sports stadium has 5,000 seats in two rings: The stadium has a ceiling height of 60 feet (18m).

There is a catwalk around the perimeter of the court, between the court and the seating areas. This catwalk is 40 feet (12m) from the floor. There are two scoreboards at either end of the stadium. The construction of the stadium is concrete and steel.

The customer does not want an under-seat, pico cell deployment, and the customer requires 802.11ac Wave 2. Which AP model is appropriate to provide coverage in the main stadium bowl?

  1. AP-228

  2. AP-344

  3. AP-365

  4. AP-375




Answer: A

Reference: https://www.google.com/url?

sa=t&rct=j&q=&esrc=s&source=web&cd=1&ved=2ahUKEwio_PnKt_jiAhVysXEKHS3hC74QFjAAegQIAxAC&url=https% 3A% 2F% 2Fcommunity.arubanetworks.com% 2Faruba% 2Fattac 2Faruba% 2FAruba-VRDs% 2F54% 2F5% 2FAruba_VHD_VRD_Planning_Guide.pdf&usg=AOvVaw1eQmHge6ZyitjnaCW rKI1z


Question: 55


Refer to the exhibit.

A customer has a wired infrastructure shown in the exhibit. The customer is in the process of expanding their wireless services. They will now add a new wireless solution, with mobility controllers (MCs) connected as shown. The new wireless solution will support a total of 450 APs and about 26,000 wireless devices. It must provide seamless roaming across the entire campus.

After the new deployment, both wired and wireless devices experience IP connectivity issues.

Which change to the existing infrastructure should the architect recommend to support all of the customer requirements? A. The MCs should be moved to the aggregation layer, and more MCs added.

  1. The core and aggregation switches should disable Virtual Switching Framework (VSF).

  2. The core switches should be replaced with switches that have larger ARP tables.

  3. The wired VLANs should be combined into a single VLAN and /16 subnet.




Answer: B



Question: 56


A customer has an existing Aruba network, which currently supports up to 9,000 wireless client devices. The existing network includes these components: Four 7210 MCs

Five 7030 MCs

200 AP-303HRs

300 AP-345s

The customer wants to convert to an ArubaOS 8.x architecture. The architect plans to deploy a virtual MM. Which exhibit shows the correct BOM for the MM?

A.

B.

C.


D.




Answer: C



Question: 57


A customer has multiple medium and large branch sites, each of which requires between 8 and 16 APs and supports between 200 and 600 wireless clients. Every branch site has an internet connection, which it uses to reach the central data center. The customer would prefer the WAN links to be optimized in the solution.

Each side handles between 1 and 2 Gbps of traffic, most of which goes to the central data center. The data center has 7210 controllers for terminating the VPN connections. Which branch office solution best meets the customer needs?

  1. CAPs and branch office controllers with an SD-WAN license

  2. IAPs and no branch office controllers

  3. CAPs and branch office controllers

  4. RAPs and no branch office controllers




Answer: B



Question: 58


Refer to the exhibits.

Exhibit 1. Existing wiring plan:

Exhibit 2. Current proposal:

A customer has a building that needs a switch upgrade. The customer would like at least 20Gbps for the uplink bandwidth out of each closet. The building writing plan is shown in Exhibit 1. The customer will not consider any cable upgrades at this point. The current proposal is shown in Exhibit 2.

Which correction must architect make to the proposal to meet the customer requirements?

  1. Change the SR transceivers for each link between the writing closet switches and the network core to LRM transceivers.

  2. Add an aggregation layer, and connect writing closet switches to the aggregation layer on Smart Rate ports.

  3. Add an aggregation layer, and connect writing closet switches to the aggregation layer with SFP+ SR transceivers.

  4. Add a mode conditioning cable for each link between the writing closet switches and the network core.




Answer: D



Question: 59


What is one customer requirement that can drive the need for a relatively dense AP deployment, in which the coverage areas of at least three AP radios overlap?

  1. support for beacon management

  2. AP operation as hybrid AMs for IDS/WIPS

  3. the deployment of dual 5GHz radio APs

  4. location tracking of wireless IoT devices



Answer: D



Question: 60


Refer to the exhibit.

An architect has planned the wireless and wired access layers for a network upgrade. The entire solution must support 9,000 wireless devices and 2,250 wired endpoints.

The campus core must meet these requirements: no more than 4:1 oversubscription on the links to the data center switch-level redundancy near instant failover if one core switch fails link aggregations between access layer and core same switch software used across the entire campus Which exhibit shows a campus core that meets the customer needs?

A.


B.

C.

D.




Answer: B