Question: 41
Audit trail is established
Only 1 is true
Only 2 is true
Both land 2are true
Neither 1 or 2 is true
Question: 42
Which activity includes addressing the disadvantages of ‘doing nothing’ to those stakeholders that object to the programme?
Analyse stakeholders
Sum ma rise risks
Carry out a health check
Conduct a visioning workshop
Question: 43
Which is a purpose of a summary risk profile?
Explain the programme risk exposure in monetary terms
Show the relationship between critical risks in a programme
Highlight any low probability benefits that are being managed as opportunity risks
Determine the residual risk exposure, assuming that planned mitigation actions are successful
Question: 44
Which describes an impact of a risk?
Effect on the programme if something goes wrong
An event that might increase a programme’s outcome
The amount of risk that will be tolerated
Possibility that something will go wrong
Question: 45
Which is evidenced by the Business Case?
Continuing affordability of the programme
Responsibility for managing the Business Change Team
Information about what will be subject to review
Risk responses for the initial programme risks
Question: 46
Which statement relates to preparing the programme plan?
Defining the approach to risk management
Describing deliverables to be produced in Defining a Programme
Appointing the Senior Responsible Owner
Processing large amounts of information
Question: 47
Which is represented in a summary risk profile?
Category of risk response
Impact of an issue
Likelihood of a risk
Cause of a risk
Question: 48
Which statement relates to preparing the programme plan?
Defining the approach to risk management
Describing deliverables to be produced in Defining a Programme
Appointing the Senior Responsible Owner
Processing large amounts of information
Question: 49
Which part of the scope of programme quality is MOST likely to be concerned with making best use of skills and experience?
Standards management
People management
Process management
Communications management
Question: 50
What role description includes support for project assurance and health checks which is independent of the projects?
Programme Manager
Business Change Manager
Senior Responsible Owner
Programme Office