Question: 32
Relative humidity is
a measure of the amount of moisture in the air compared to saturation level.
a measure of the amount of moisture in the air compared to the air temperature.
the lowest temperature at which moisture forms on a steel surface.
the highest temperature at which moisture forms on a steel surface.
Question: 33
Upon arrival of coating materials, the inspector should
review coating contractors’ plans for storage of coating materials and confirm they meet national, local and owners’ fire and environmental regulations.
observe and document the amount of material and batch numbers.
observe aryl document that the applicator WFT at regular intervals during application.
observe and document time frame and environmental conditions between each coat.
Question: 34
Which one of these elements is not necessary for corrosion to occur:
Anode
Cathode
Reference Cell
Electrolyte
Question: 35
Conventional spray is a good choice when:
High production rates are required
High quality finishes are required
High transfer efficiency is required
High viscosity coatings are being applied
Question: 36
Fine cracks in the surface of a coating that rarely reach the substrate are called
cracking.
alligatoring.
checking.
blistering.
Question: 37
Using SSPC Vis 1 as a guide when performing a visual inspection of a steel surface prior to surface preparation a NACE Inspector would assign which designations to the surface condition:
Rust Grades A-D
Surface Conditions E-G
Rust Grades 1-4
Surface Condition H
Question: 38
The initial steel condition is important to the NACE Inspector because:
If the steel is pitted more coating will be required
Less abrasive is need if the mill Scale s gone
It affects the final appearance after blasting
The Inspector may have to reject the Steel
Question: 39
It is good practice for the NACE Inspector to have instrument calibration certificates available:
At all times
In the office only
In the field only
Only if the specification requires it
Question: 40
If a contractor is using a poorly maintained compressor to supply air for abrasive blast cleaning and conventional airspray, the coating inspector should perform a
dry film thickness (DEI) measurement.
wet film thickness (WFT) measurement.
blotter test for the presence of oil and water.
vial lest.