PMI-100 Dumps

PMI-100 Braindumps PMI-100 Real Questions PMI-100 Practice Test

PMI-100 Actual Questions


PMI


PMI-100


Certified Associate in Project


https://killexams.com/pass4sure/exam-detail/PMI-100


QUESTION: 345

When cost variance is negative and schedule variance is positive, the project is:


  1. under budget and behind schedule.

  2. over budget and ahead of schedule.

  3. on schedule.

  4. complete; all planned values have been earned.


Answer: B


QUESTION: 346

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?


  1. Reserve analysis

  2. Three-point estimating

  3. Parametric estimating

  4. Analogous estimating


Answer: D


QUESTION: 347

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:


  1. majority rule technique.

  2. nominal group technique.

  3. Delphi technique,

  4. idea/mind mapping technique.

Answer: B


QUESTION: 348

At which stage of team development do members begin to work together, adjust work habits, and trust each other?


  1. Forming

  2. Storming

  3. Norming

  4. Performing


Answer: C


QUESTION: 349

Which of the following can be used as an input for Define Scope?


  1. Product analysis

  2. Project charter

  3. Scope baseline

  4. Project scope statement


Answer: B


QUESTION: 350

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:


  1. Manage Stakeholder Expectations.

  2. Monitor and Control Risks.

  3. Plan Risk Management.

  4. Report Performance.


Answer: A


QUESTION: 351

Which of the following is a tool and technique used to monitor risk?


  1. Technical performance measurement

  2. Cost performance baseline

  3. Benchmarking

  4. Cost of quality


Answer: A


QUESTION: 352

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?


  1. Sensitivity analysis

  2. Three-point estimate

  3. Modeling and simulation

  4. Expected monetary value analysis


Answer: D


QUESTION: 353

Which of the following is an output of Close Procurements?


  1. Accepted deliverables

  2. Organizational process assets updates

  3. Managing stakeholder expectations

  4. Performance reports


Answer: B


QUESTION: 354

The probability and impact matrix is primarily used to:


  1. Quantify risk issues for trends during a quality audit.

  2. Develop a risk register for risk planning.

  3. Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.

  4. Define risk and compare impacts during Perform Quantitative Risk Analysis.


Answer: C