image


PMI-RMP Dumps

PMI-RMP Braindumps PMI-RMP Real Questions PMI-RMP Practice Test

PMI-RMP Actual Questions


PMI


PMI-RMP


PMI Risk Management Professional


https://killexams.com/pass4sure/exam-detail/PMI-RMP


Question #428


In what way can the risk manager determine when poor risk planning techniques are influencing the scope, schedule, quality, and/or budget of the project?


image

  1. Evaluate the results of the Monte Carlo analysis.

    image

  2. Document and periodically update project risk information

    image

  3. Monitor project metrics and performance information.

    image

  4. Update the risk management plan.


Answer: C Question #429

How can the project manager rank competing stakeholder priorities for all the identified risks?


image

  1. Perform qualitative and quantitative risk analysis.

    image

  2. Engage the project sponsor to decide.

    image

  3. Refer to stakeholder analysis prioritization tree.

    image

  4. Perform a review of organizational process assets.


Answer: A Question #430

A project team is conducting initial risk planning. What other risk-related task should the project manager perform?


image

  1. Identifying the risk threshold

    image

  2. Determining the risk register headings

    image

  3. Scoring the risks utilizing the risk matrix

    image

  4. Prioritizing the risks in the risk register


Answer: A Question #431

What are the critical success factors for the Plan Risk Management process?


image

  1. Mitigate all risks, engage stakeholders, and follow organizational policies.

    image

  2. Identify and address barriers, engage stakeholders, and follow organizational policies.

    image

  3. Contingency reserves engage stakeholders and follow organizational policies.

    image

  4. Identify and address barriers, engage stakeholders, and follow government regulations.


Answer: B Question #432

A project team's risk facilitator identifies a number of risks and must prioritize them based on the organization's risk appetite levels. Which technique should be used?


image

  1. PERT

    image

  2. Stakeholder risk profile analysis

  3. Project scope statement analysis

    image

  4. Monte Carlo technique


Answer: B Question #433

A risk manager wants to determine which risks are going to have the highest impact on a project. Which of the following techniques should the risk manager use?


image

  1. Assumptions analysis

    image

  2. Sensitivity analysis

    image

  3. Root cause analysis

    image

  4. Prioritization matrices


Answer: D Question #434

The project manager wants risk metrics established for the new project. Which of the following metrics listed is best suited for this purpose?


image

  1. Effectiveness of the work breakdown structure

    image

  2. Number of approved project change requests

    image

  3. Number of detects identified

    image

  4. Effectiveness of response plans


Answer: D Question #435

Which of the following would a proactive risk manager do during the Monitoring and Controlling Process?


image

  1. Develop risk responses, create risk management plan, and stay alert for risk events.

    image

  2. Update the lessons learned documents, develop risk responses, and create the risk management plan.

    image

  3. Review identified risks, stay alert for risk events, and remind team members to keep the risk manager informed about risk triggers.

    image

  4. Review lessons learned document to identify risks, quantity risks, and lower impact ratings.


Answer: C Question #436

A cost analyst team member asks the project manager for the latest risk data for inclusion with the cost estimates for the project. Which tool should the cost analyst team member use to identify the probability of achieving specific cost targets?


image

  1. Monte Carlo analysis

    image

  2. Decision tree analysis

    image

  3. Analogous estimating

    image

  4. Brainstorming


Answer: A Question #437

Most risks are assessed for probability and impact. Which of the following are other factors that should be considered?


image

  1. Urgency and complexity

    image

  2. Manageability and cost

    image

  3. Urgency and manageability

    image

  4. Manageability and complexity


Answer: C Question #438

A pharmaceutical company undertakes a new, year-long research and development (R&D) project. The company pursues high margins on investments and an aggressive growth strategy. They maintain a central program management office (PMO) to assist with new projects and record data on past project performance.

The company leadership regularly makes decisions regarding the full suite of company projects and requires comparative data and reports. Project leadership is well-versed in risk management and the PMO requires full documentation of project management artifacts.

Based on the characteristics of this new project, which of the following best describes the risk strategy for the project?


image

  1. Low stakeholder risk appetite, leverage historical project planning data, develop standard metrics and reports, and develop a formal risk management plan.

    image

  2. High stakeholder risk appetite; leverage historical project planning data, develop standard metrics and reports, develop a formal risk management plan.

    image

  3. High stakeholder risk appetite; leverage historical project planning data, utilize informal metrics and reports, develop risk management training.

    image

  4. Low stakeholder risk appetite; collect new project data, create custom metrics and reports, and develop a formal risk management plan.


Answer: B Question #439

Which of the following should the risk manager consider as external environmental factors when creating the risk management plan?


image

  1. Government regulations, industry best practice templates, organizational standard processes, and competitor landscape

    image

  2. Government regulations, industry standards, conditions of the marketplace, and competitor landscape

    image

  3. Government regulations, risk categories, organizational standard processes, and competitor landscape

    image

  4. Government regulations, human resource policies and procedures, organizational standard processes, and competitor landscape


Answer: B Question #440

A project manager is leading a project review meeting with the risk manager and the other project stakeholders. Which of the following are typical risk-related agenda items for a project review meeting?


image

  1. Enterprise environmental factors and the risk register

    image

  2. Risks closed in the last period and the risk appetite of the organization

    image

  3. Organizational process assets and the risk register

    image

  4. Risks closed in the last period and the trigger conditions that have occurred


Answer: D Question #441

As part of identifying the risk appetite of project stakeholders, the project manager must first identify the stakeholders. Which of the following inputs are used to identify project stakeholders?


image

  1. Project charter, management reserve, enterprise environmental factors, and organizational process assets

    image

  2. Project management plan, human resource plan, enterprise environmental factors, and organizational process assets

    image

  3. Project charter, bid documents, enterprise environmental factors, and organizational process assets

    image

  4. Project charter, communications management plan, enterprise environmental factors, and organizational process assets

Answer: C Question #442

The project manager receives an updated project schedule from a sub team detailing the deliverables, dates, and durations for a critical milestone on the development and testing for offshore activities. This report is received one hour before a meeting with the chief executive officer (CEO) to present an updated master schedule of the critical path. The CEO has been promised a discussion on the project schedule several times. However, based on the recent update from the off-shore team, the project manager realizes this new schedule is not realistic. There are new risks associated with it and it is not well thought out. Some key stakeholders want to present this revised plan to the CEO. This meeting has been postponed twice already.

Which action should the project manager take before meeting with the CEO?


image

  1. Talk to the stakeholders before the meeting to discuss the options and ask their opinion.

    image

  2. Present the revised master schedule to the CEO with the caveat that its being updated as new information is received, and these are the current dates at this point.

    image

  3. Request the meeting be re-scheduled before presenting the master schedule to the CEO, stating that new major risks were identified and need to be assessed thoroughly.

    image

  4. Present the revised schedule to the CEO and only answer questions about validity, if asked.


Answer: A Question #443

Which of the following are examples of relevant data gathering tools?


image

  1. Risk response plan and interviews

    image

  2. Questionnaires and historical data

    image

  3. Work breakdown structure an historical data

    image

  4. Work breakdown structure and interviews


Answer: B


image

6$03/( 48(67,216


7KHVH TXHVWLRQV DUH IRU GHPR SXUSRVH RQO\ )XOO YHUVLRQ LV XS WR GDWH DQG FRQWDLQV DFWXDO TXHVWLRQV DQG DQVZHUV


.LOOH[DPV FRP LV DQ RQOLQH SODWIRUP WKDW RIIHUV D ZLGH UDQJH RI VHUYLFHV UHODWHG WR FHUWLILFDWLRQ H[DP SUHSDUDWLRQ 7KH SODWIRUP SURYLGHV DFWXDO TXHVWLRQV H[DP GXPSV DQG SUDFWLFH WHVWV WR KHOS LQGLYLGXDOV SUHSDUH IRU YDULRXV FHUWLILFDWLRQ H[DPV ZLWK FRQILGHQFH +HUH DUH VRPH NH\ IHDWXUHV DQG VHUYLFHV RIIHUHG E\ .LOOH[DPV FRP


$FWXDO ([DP 4XHVWLRQV .LOOH[DPV FRP SURYLGHV DFWXDO H[DP TXHVWLRQV WKDW DUH H[SHULHQFHG LQ WHVW FHQWHUV 7KHVH TXHVWLRQV DUH XSGDWHG UHJXODUO\ WR HQVXUH WKH\ DUH XS WR GDWH DQG UHOHYDQW WR WKH ODWHVW H[DP V\OODEXV %\ VWXG\LQJ WKHVH DFWXDO TXHVWLRQV FDQGLGDWHV FDQ IDPLOLDUL]H WKHPVHOYHV ZLWK WKH FRQWHQW DQG IRUPDW RI WKH UHDO H[DP


([DP 'XPSV .LOOH[DPV FRP RIIHUV H[DP GXPSV LQ 3') IRUPDW 7KHVH GXPSV FRQWDLQ D FRPSUHKHQVLYH FROOHFWLRQ RI TXHVWLRQV DQG DQVZHUV WKDW FRYHU WKH H[DP WRSLFV %\ XVLQJ WKHVH GXPSV FDQGLGDWHV FDQ HQKDQFH WKHLU NQRZOHGJH DQG LPSURYH WKHLU FKDQFHV RI VXFFHVV LQ WKH FHUWLILFDWLRQ H[DP


3UDFWLFH 7HVWV .LOOH[DPV FRP SURYLGHV SUDFWLFH WHVWV WKURXJK WKHLU GHVNWRS 9&( H[DP VLPXODWRU DQG RQOLQH WHVW HQJLQH 7KHVH SUDFWLFH WHVWV VLPXODWH WKH UHDO H[DP HQYLURQPHQW DQG KHOS FDQGLGDWHV DVVHVV WKHLU UHDGLQHVV IRU WKH DFWXDO H[DP 7KH SUDFWLFH WHVWV FRYHU D ZLGH UDQJH RI TXHVWLRQV DQG HQDEOH FDQGLGDWHV WR LGHQWLI\ WKHLU VWUHQJWKV DQG ZHDNQHVVHV


*XDUDQWHHG 6XFFHVV .LOOH[DPV FRP RIIHUV D VXFFHVV JXDUDQWHH ZLWK WKHLU H[DP GXPSV 7KH\ FODLP WKDW E\ XVLQJ WKHLU PDWHULDOV FDQGLGDWHV ZLOO SDVV WKHLU H[DPV RQ WKH ILUVW DWWHPSW RU WKH\ ZLOO UHIXQG WKH SXUFKDVH SULFH 7KLV JXDUDQWHH SURYLGHV DVVXUDQFH DQG FRQILGHQFH WR LQGLYLGXDOV SUHSDULQJ IRU FHUWLILFDWLRQ H[DPV


8SGDWHG &RQWHQW .LOOH[DPV FRP UHJXODUO\ XSGDWHV LWV TXHVWLRQ EDQN DQG H[DP GXPSV WR HQVXUH WKDW WKH\ DUH FXUUHQW DQG UHIOHFW WKH ODWHVW FKDQJHV LQ WKH H[DP V\OODEXV 7KLV KHOSV FDQGLGDWHV VWD\ XS WR GDWH ZLWK WKH H[DP FRQWHQW DQG LQFUHDVHV WKHLU FKDQFHV RI VXFFHVV


7HFKQLFDO 6XSSRUW .LOOH[DPV FRP SURYLGHV IUHH [ WHFKQLFDO VXSSRUW WR DVVLVW FDQGLGDWHV ZLWK DQ\ TXHULHV RU LVVXHV WKH\ PD\ HQFRXQWHU ZKLOH XVLQJ WKHLU VHUYLFHV 7KHLU FHUWLILHG H[SHUWV DUH DYDLODEOH WR SURYLGH JXLGDQFH DQG KHOS FDQGLGDWHV WKURXJKRXW WKHLU H[DP SUHSDUDWLRQ MRXUQH\


'PS .PSF FYBNT WJTJU IUUQT LJMMFYBNT DPN WFOEPST FYBN MJTU

.LOO \RXU H[DP DW )LUVW $WWHPSW *XDUDQWHHG