Question: 341

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?


  1. Perform Quality Control

  2. Perform Quality Assurance

  3. Plan Quality

  4. Report Performance




Answer: A



Question: 342

A collection of projects or programs are known as which of the following?


  1. Groups

  2. Portfolios

  3. Collections

  4. Organizations




Answer: B



Question: 343

What project management context refers to a collection of projects or programs that are grouped together to meet strategic business objectives?


  1. Program management

  2. Portfolio management

  3. Strategic management

  4. Business management



Question: 344

Individuals and organizations that are actively involved in or whose interests may be affected by a project are called which of the following?


  1. Organizational members

  2. Stakeholders

  3. Project team members

  4. Project managers




Answer: B



Question: 345

Which of the following is an output of the develop project team process?


  1. Approved corrective actions

  2. Work performance information

  3. Team performance assessment

  4. Staffing management plan update




Answer: C



Question: 346

The process of obtaining the stakeholders' formal acceptance of the completed project scope and associated deliverables is which of the following?


  1. Scope definition

  2. Scope verification

  3. Project plan approval

  4. Scope control

    Answer:
    B
    Question:
    347


  1. Perform Qualitative Risk Analysis

  2. Identify Risks

  3. Plan Risk Management

  4. Perform Quantitative Risk Analysis




Answer: B



Question: 348

Which is an input to the Verify Scope process?


  1. Performance report

  2. Work breakdown structure (WBS)

  3. Requested changes

  4. Project management plan




Answer: D



Question: 349

Which is a tool or technique used in Define Scope?


  1. Templates, forms, and standards

  2. Change requests

  3. Product analysis

  4. Project assumptions




Answer: C



Question: 350

A procurement management plan is a subsidiary of which other type of plan?


  1. Resource plan

  2. Project management plan

  3. Cost control plan




Answer: B