PR2F Dumps PR2F Braindumps
PR2F Real Questions PR2F Practice Test PR2F Actual Questions
PRINCE2 Foundation
https://killexams.com/pass4sure/exam-detail/PR2F
Question: 242
Which is a purpose of the Risk theme?
Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
Establish a cost-effective procedure to identify, assess and control uncertainty
Establish mechanisms to control any unacceptable deviations from plan
Establish mechanisms to manage risks at the corporate or programme level of an organization
Answer: B
Question: 243
In what process is the authorization to deliver the project’s products given?
Starting up a Project
Initiating a Project
Managing a Stage Boundary
Directing a Project
Answer: D
Question: 244
Which of the following is NOT part of quality planning?
Define quality responsibilities
Gain acceptance of the project product
Agree acceptance criteria
Set quality tolerances
Answer: B
Question: 245
Which should be provided by a project mandate?
Terms of reference
Detailed Business Case
Stage tolerances
Initiation Stage Plan
Answer: A
Question: 246
Which is an objective of the Starting up a Project process?
Identify who will be responsible for creating the Project Plan
Agree how the project will be monitored and controlled after initiation
Authorize the Project Manager to proceed with the initiation stage
Agree how issues and changes will be identified, assessed and controlled
Answer: A
Question: 247
Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,
Management strategies
Plan
Stakeholder interests
Time-driven controls
Answer: B
Question: 248
If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
Senior User
Executive
Corporate/programme management
Senior Supplier
Answer: C
Question: 249
Which is an objective of the quality review technique?
To identify a product’s quality criteria
To provide assurance that the project is being conducted properly
To assess that a product conforms to set criteria
To ensure that staff are properly trained in the quality methods
Answer: C
Question: 250
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
Risk category
Risk description
Risk response
Risk status
Answer: C
Question: 251
If an informal issue is defined as a problem or concern, where should it first be recorded?
Issue Register
Risk Register
Daily Log
Exception Report
Answer: C
Question: 252
Which of the following statements about the Project Initiation Documentation are true?
The Project Initiation Documentation is used to ensure that a sound basis exists exists before the Project Board authorizes a project.
The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project.
Only 1 is true
Only 2 is true
Both 1 and 2 are true
Neither 1 or 2 are true
Answer: C
Question: 253
Which is the purpose of the Change theme?
Prevent change to baselined products
Identify, assess and control any potential and approved changes to baselined products
Establish mechanisms to monitor and compare actual achievements against those planned
Assess and control uncertainty
Answer: B