PSA-2023 Dumps PSA-2023 Braindumps

PSA-2023 Real Questions PSA-2023 Practice Test PSA-2023 Actual Questions


Certinia


PSA-2023


PSA System Administrator 2023


https://killexams.com/pass4sure/exam-detail/PSA-2023

Question: 237


You have set up a Flow to automatically assign a resource's manager to the approver field on Timecards. Users have reported that submitted Timecards are going to the Project Manager for approval and not the resource's manager.


Of the following, which could be a reason for this?


  1. PSA requires that only Project Managers can approve Timecards

  2. The process builder to assign the resource's manager is not active

  3. The configuration option Assign Project Manager To Time card Approver is set to True


Answer: A Question: 238

Your company has both full time and part time resources. From a Human Resources perspective, part time resources can work any number of hours per week. From a Resource Planning perspective, management has agreed that part time workers can be estimated at 20 hours per week.


Based on this information, how many work calendars should be created?


  1. One full time work calendar, and one work calendar for each unique part time contract

  2. One full time work calendar, and one part time work calendar

  3. One full time work calendar, one part time work calendar, and one generic flexible work calendar


Answer: C Question: 239

Project Managers would like to display several fields prominently on the Project Lightning Page. Which PSA Lightning Component could you use to meet this need?

  1. FF Field Overview

  2. FF Highlights

  3. FF PSA Field Summary


Answer: B Question: 240

You are notified that some approved Miscellaneous Adjustments records are not getting picked up in the Billing Event Generation process during month end billing.


Which two of the following system settings do you need to have in place for Miscellaneous Adjustments to get picked up in the billing run? (Choose two.)


  1. The Effective Date value on the Miscellaneous Adjustments records is within the Date range of the Time period used on the Billing Generation process.

  2. The person running the Billing Event Generation process does not have Billing Miscellaneous Adjustments permission control for the Region. Account, or Project selected on the Billing Generation process.

  3. The Transaction Category value on the Miscellaneous Adjustments record exists in the Configuration option: Billing

Categories. Answer: A,C Question: 241

Which of the following custom settings can be specific to a User?


  1. Search Resources Global

  2. Timecard Entry Ul Personal

  3. Assignment Settings


Answer: B Question: 242

Your current setup of utilization automatically subtracts PSA Holidays from the total number of hours defined in a resource's "Work Calendar."


How can utilization be configured so Holidays are not automatically subtracted?


  1. Go to App Launcher > navigate to "PSA Administration" > select "Schedule Utilization" > Navigate to the Information section > set "subtract holidays from total hours" to false

  2. Go to Ag£ Launcher > navigate to "Configuration Groups" > select "Utilization" > select "subtract holidays from total hours" > set to false

  3. Go to Ag£ Launcher > navigate to "Utilization Calculation" > select the calculation you want modified > set "subtract holidays from total hours" to false


Answer: C Question: 243

Your company's leadership noticed that the "PSA Resourcing" Lightning Component is displaying a "Default Cost Rate" column. They asked you to remove this column from the component. You edited the Resource Request Lightning Page, selected the "PSA Resourcing" component, and identified the "Column Field Set" setting.


What is the next step to complete this change?


  1. Go to Setup > navigate to the Object Manager for "Contact" > select Field Sets > remove the "Default Cost Rate" field from the field set

  2. Go to Setup > navigate to Custom Settings > open the "Resource Request" setting > populate the Field Set in the "Resource Grid Field Set"

  3. Go to Setup > navigate to the "PSA User" Permission Set > open the "Resource Request" object settings > remove field level security for the "Default Cost Rate" field


Answer: A Question: 244

An Administrator can find the majority of settings for PSA in which two of the following areas? (Choose two.)


  1. Configuration Groups

  2. Custom Settings

  3. PSA Administration Page


Answer: A,C Question: 245

You are in the process of setting up your organization's Resources and learn that Resources in France will be working a 35-hour work week.


What will you need to do to set them up with the proper work calendar?


  1. As PSA only allows one work calendar, it is best to implement a 40-hour work calendar and then create a validation rule to only allow 35 hours a week.

  2. As the Work Calendar mostly impacts Utilization, set them up with a 40-work calendar, and then include the 35- hour hour work week in your utilization calculations.

  3. Create a separate 35-hour work calendar and associate it to the French Resources, including any specific French Holidays.


Answer: C Question: 246

Your company is rolling out Skills and Certifications to encourage employees to track their skills and also decide which skills they would like to acquire. After rolling this feature out, end-users have noted they can't add their assignments to build their "Experience".


What could be causing this problem?


  1. The "Enable Experience" checkbox in the enable-skills-experience configuration option is not selected

  2. The "Enable Experience" checkbox in the Skills Management custom setting is not selected

  3. The "Enable Experience" field on the PSA contact record is not selected


Answer: C Question: 247

Currently Project Managers and Resource Managers are using Gantt. You do not want your Project Managers creating assignment, resource requests or milestones from the Gantt.


Which of the following custom settings should you configure to hide these buttons?


  1. Project Task Gantt Global Settings

  2. Gantt Global Settings

  3. Project Task Gantt Preferences


Answer: B Question: 248

In your organization, you always send 2 separate invoices to your customers C one for Timecards & Expenses and the other for Misc Adjustment type billable records.

How could this be done automatically using FinancialForce functionality?


  1. You would set the "separateMiscellaneousAdiustments" Configuration Option to 'True", so that "Timecards & Expenses" and "Misc Adjustments" are included in two separate Billing events.

  2. In the first Billing cycle, the Billing team would deselect the "Include Misc Adjustment" checkbox, to exclude those records from the Billing Event. In the second Billing cycle, they would be required to select "Include Misc Adjustment" and deselect "Include Timecards and Expenses", resulting in two separate Billing Events.

  3. You would set the "Include Misc Adjustments" settings in the "Billing" custom settings to "False", so those are included in a separate Billing Event from Timecards & Expenses.


Answer: A Question: 249

In your Company, a Resource Manager wants to provide the option for Resources to nominate themselves for upcoming work they are interested in.


How can you set this up?


  1. Enable "Self-Nominate for Resource Request" custom setting > add the "PSA Resource Self-Nomination" Lightning component to the Resource Request Detail Page

  2. Enable "Candidates Can Self-Nominate for Work" custom setting > add the "PSA Resource Self-Nomination" Lightning component to the Lightning Home page

  3. Enable "Self-Nominate for Work" custom setting > add the "PSA Self-Nomination" Lightning component to the Project Detail Page


Answer: A Question: 250

A Services manager has asked you to set up a unique "FF Navigation" lightning component on the "Services Delivery Workspace" that will provide separate options to users based on which team (business unit) they belong to.


Which two of the following actions would successfully accomplish the required setup? (Choose two.)


  1. The system admin can enable the "Hide Navigation Sections" setting within the "FF Navigation" lightning component to support different teams

  2. The system admin can clone the page and create two unique pages that have the "FF Navigation" lightning component configured for their respective team

  3. The system admin can add the "FF Navigation" component to the page twice and setup component visibility rules to ensure the right team sees their navigation


Answer: A,B,C Question: 251

Managers within your company are using the Resource Planner to check a resource's availability but report that they are not seeing the Availability column on the Resource Planner.


Which two of the following could be causing this issue? (Choose two.)


  1. Utilization Ermine checkbox is deselected under Utilization custom settinqs

  2. Resource Availability column is not selected under the Resource Planner columns list

  3. Managers don't have the field level access to Resource Availability


Answer: A,B Question: 252

Your company hired its first part-time employee that needs to be set up as a Consultant in PSA. They will work about 20 hours a week instead of the normal 40 hours a week.


Which of the following steps should you take to ensure this consultant's utilization calculation will be calculated correctly?


  1. Create a new "Role" indicating the user is a Part Time Consultant

  2. Create a new Part Time "Work Calendar" for 20 hours

  3. Create a new "Utilization Calculation" labeled Part Time


Answer: B Question: 253

On the Resource Request Lightning page, your team is requesting changes to the Filter panel on the right side of the page, and would like to know what configurations are possible.


Which two of the following configurations are available for the Filter panel? (Choose two.)


  1. Add or Remove the Start and End Date fields

  2. Add or Remove Region. Practice, and Group filters

  3. Add or Remove the Skills filters


Answer: A,B Question: 254

The Finance Team is interested in limiting the amount for a particular type of expense company-wide. Of the following, which is the best solution to accomplish this?

  1. Set up an Expense Limit that will limit the expense based on the Expense Type on the Expense Limit record at the global region level.

  2. Set up an Expense Limit that will limit the expense based on the Expense Type on the RPG record.

  3. Set up an Expense Limit that will limit the expense based on the Expense Type on the Resource Record.


Answer: A Question: 255

To update Resource Roles in PSA, you will need to update the picklists of which two of the following objects? (Choose two.)


  1. Contact

  2. Work Calendars

  3. Assignment Answer: A,C Question: 256

The time periods in your org run through 2024. Your Finance team wants to start building forecast models through

2030.


What is the best way to help the Finance team accomplish their task?


  1. Contact FinancialForce Onboarding and have them assist you jn uploadinq a "csvfile with the correct time periods for the years 2025-2030 into your org

  2. Use dataloader.io or Data Import Wizard to upload a "csvfile with the correct time periods for the years 2025-2030 into your org

  3. Contact FinancialForce Support or your Partner to open a ticket, requestinq that Onboarding help load the required time periods to ensure Actuals remain intact in your org


Answer: C