image


PSM-I Dumps PSM-I Braindumps

PSM-I Real Questions PSM-I Practice Test PSM-I Actual Questions


Scrum


PSM-I


Professional Scrum Master I - 2023


https://killexams.com/pass4sure/exam-detail/PSM-I


Question: 307


Which of the following is required by Scrum? (Choose all that apply.) A . Sprint Retrospective.

B . Members must be stand up at the Daily Scrum. C . Sprint Burndown Chart.

D . Release planning. E . All of the above.


Answer: A


Question: 308


As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle.


Which two are valid actions? (Choose two.)

A . Recruit additional Development Team members before the work can begin.

B . The Development Team ensures that the Product Owner is aware, starts the Sprint, and monitors progress. C . Cancel the Sprint.

D . Remove or change selected Product Backlog items.

E . The Development Team works overtime during this Sprint.


Answer: BD


Question: 309


When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint? A . Yes, but only for Scrum Teams whose work has dependencies.

B . Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done. C . No, each Scrum Team stands alone.

D . No, that is far too hard and must be done in a hardening Sprint.


Answer: B


Question: 310


Which two things should the Development Team do during the first Sprint? (Choose two.) A . Make up a plan for the rest of the project.

B . Analyze, describe, and document the requirements for the subsequent Sprints.

C . Develop at least one piece of functionality.

D . Analyze, design, and describe the complete architecture and infrastructure. E . Create an increment of potentially releasable software.


Answer: CE


Question: 311


A properly functioning Scrum Team will have at least one Release Sprint and may well have several. A . True

B . False


Answer: A


Question: 312


Scrum is a methodology that tells in detail how to build software incrementally. A . True

B . False


Answer: B


Question: 313


In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn’t figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able to agree on a Sprint Goal, however.


Which of the following two actions should the Scrum Master support? (Choose two.)

A . Cancel the Sprint. Send the entire team to an advanced Scrum training and then start a new Sprint.

B . Forecast the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial design and plan. Once the time-box for the Sprint Planning meeting is over, start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint.

C . Continue the Sprint Planning meeting past its time-box until an adequate number of Product Backlog items are well enough understood for the Development Team to make a complete forecast. Then start the Sprint.

D . Discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur. E . Ask everyone to take as much time as needed to analyze the Product Backlog first, and then reconvene another Sprint Planning meeting.


Answer: BD


Question: 314


The Product Owner must release each Increment to production. A . When it makes sense.

B . To make sure the Development Team is done every Sprint. C . Whenever the product is free of defects.

D . Without exception.


Answer: A


Question: 315


Which statement best describes Scrum?

A . A defined and predictive process that confirms to the principles of Scientific Management. B . A complete methodology that defines how to develop software.

C . A cookbook that defines best practices for software development.

D . A framework within which complex products in complex environments are developed.


Answer: D


Question: 316


Who should make sure everyone on the Development Team does his or her tasks for the Sprint? A . The Project Manager.

B . The Product Owner. C . The Scrum Master.

D . The Development Team. E . All of the above.


Answer: D


Question: 317


How much time is required after a Sprint to prepare for the next Sprint?

A . The break between Sprints is time-boxed to 1 week for 30 day Sprints, and usually less for shorter sprints. B . Enough time for the requirements for the next Sprint to be determined and documented.

C . Enough time for the Development team to finish the testing from the last Sprint. D . None. A new Sprint starts immediately following the end of the previous Sprint. E . All of the above are allowed depending on the situation.


Answer: D


Question: 318


What are three ways Scrum promotes self-organization? (Choose three.) A . By not allowing documentation.

B . By the Development Team deciding what work to do in a Sprint. C . By preventing stakeholders from entering the development room. D . By removing titles for Development Team members.

E . By being a lightweight framework.

Answer: BDE


Question: 319


The Daily Scrum is an event that happens every day.


What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.) A . Opportunities to insect and adapt the Sprint Backlog are lost.

B . Impediments are raised and resolved more slowly.

C . The Product Owner cannot accurately report progress to the stakeholders. D . Too much work is spent updating the Scrum board before the meeting.

E . The Scrum Master loses the ability to update the Gantt chart properly.


Answer: ACB


Question: 320


What does it mean to say that an event has a time-box? A . The event must happen at a set time.

B . The event must happen by a given time.

C . The event must take at least a minimum amount of time.

D . The event can take no more than a maximum amount of time.


Answer: D


Question: 321


For which is the Scrum Master responsible?

A . Managing the performance of the Scrum Team.

B . The meetings and the objectives that a Scrum Team sets for itself. C . The Scrum framework being adopted and used properly.

D . Keeping track of resource allocation.


Answer: C


Question: 322


Who determines when it is appropriate to update the Sprint Backlog during a Sprint? A . The Project Manager.

B . The Development Team. C . The Scrum Team.

D . The Product Owner.


Answer: B


image

6$03/( 48(67,216


7KHVH TXHVWLRQV DUH IRU GHPR SXUSRVH RQO\ )XOO YHUVLRQ LV XS WR GDWH DQG FRQWDLQV DFWXDO TXHVWLRQV DQG DQVZHUV


.LOOH[DPV FRP LV DQ RQOLQH SODWIRUP WKDW RIIHUV D ZLGH UDQJH RI VHUYLFHV UHODWHG WR FHUWLILFDWLRQ H[DP SUHSDUDWLRQ 7KH SODWIRUP SURYLGHV DFWXDO TXHVWLRQV H[DP GXPSV DQG SUDFWLFH WHVWV WR KHOS LQGLYLGXDOV SUHSDUH IRU YDULRXV FHUWLILFDWLRQ H[DPV ZLWK FRQILGHQFH +HUH DUH VRPH NH\ IHDWXUHV DQG VHUYLFHV RIIHUHG E\ .LOOH[DPV FRP


$FWXDO ([DP 4XHVWLRQV .LOOH[DPV FRP SURYLGHV DFWXDO H[DP TXHVWLRQV WKDW DUH H[SHULHQFHG LQ WHVW FHQWHUV 7KHVH TXHVWLRQV DUH XSGDWHG UHJXODUO\ WR HQVXUH WKH\ DUH XS WR GDWH DQG UHOHYDQW WR WKH ODWHVW H[DP V\OODEXV %\ VWXG\LQJ WKHVH DFWXDO TXHVWLRQV FDQGLGDWHV FDQ IDPLOLDUL]H WKHPVHOYHV ZLWK WKH FRQWHQW DQG IRUPDW RI WKH UHDO H[DP


([DP 'XPSV .LOOH[DPV FRP RIIHUV H[DP GXPSV LQ 3') IRUPDW 7KHVH GXPSV FRQWDLQ D FRPSUHKHQVLYH FROOHFWLRQ RI TXHVWLRQV DQG DQVZHUV WKDW FRYHU WKH H[DP WRSLFV %\ XVLQJ WKHVH GXPSV FDQGLGDWHV FDQ HQKDQFH WKHLU NQRZOHGJH DQG LPSURYH WKHLU FKDQFHV RI VXFFHVV LQ WKH FHUWLILFDWLRQ H[DP


3UDFWLFH 7HVWV .LOOH[DPV FRP SURYLGHV SUDFWLFH WHVWV WKURXJK WKHLU GHVNWRS 9&( H[DP VLPXODWRU DQG RQOLQH WHVW HQJLQH 7KHVH SUDFWLFH WHVWV VLPXODWH WKH UHDO H[DP HQYLURQPHQW DQG KHOS FDQGLGDWHV DVVHVV WKHLU UHDGLQHVV IRU WKH DFWXDO H[DP 7KH SUDFWLFH WHVWV FRYHU D ZLGH UDQJH RI TXHVWLRQV DQG HQDEOH FDQGLGDWHV WR LGHQWLI\ WKHLU VWUHQJWKV DQG ZHDNQHVVHV


*XDUDQWHHG 6XFFHVV .LOOH[DPV FRP RIIHUV D VXFFHVV JXDUDQWHH ZLWK WKHLU H[DP GXPSV 7KH\ FODLP WKDW E\ XVLQJ WKHLU PDWHULDOV FDQGLGDWHV ZLOO SDVV WKHLU H[DPV RQ WKH ILUVW DWWHPSW RU WKH\ ZLOO UHIXQG WKH SXUFKDVH SULFH 7KLV JXDUDQWHH SURYLGHV DVVXUDQFH DQG FRQILGHQFH WR LQGLYLGXDOV SUHSDULQJ IRU FHUWLILFDWLRQ H[DPV


8SGDWHG &RQWHQW .LOOH[DPV FRP UHJXODUO\ XSGDWHV LWV TXHVWLRQ EDQN DQG H[DP GXPSV WR HQVXUH WKDW WKH\ DUH FXUUHQW DQG UHIOHFW WKH ODWHVW FKDQJHV LQ WKH H[DP V\OODEXV 7KLV KHOSV FDQGLGDWHV VWD\ XS WR GDWH ZLWK WKH H[DP FRQWHQW DQG LQFUHDVHV WKHLU FKDQFHV RI VXFFHVV


7HFKQLFDO 6XSSRUW .LOOH[DPV FRP SURYLGHV IUHH [ WHFKQLFDO VXSSRUW WR DVVLVW FDQGLGDWHV ZLWK DQ\ TXHULHV RU LVVXHV WKH\ PD\ HQFRXQWHU ZKLOH XVLQJ WKHLU VHUYLFHV 7KHLU FHUWLILHG H[SHUWV DUH DYDLODEOH WR SURYLGH JXLGDQFH DQG KHOS FDQGLGDWHV WKURXJKRXW WKHLU H[DP SUHSDUDWLRQ MRXUQH\


'PS .PSF FYBNT WJTJU IUUQT LJMMFYBNT DPN WFOEPST FYBN MJTU

.LOO \RXU H[DP DW )LUVW $WWHPSW *XDUDQWHHG