Question: 87
Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?
Verify the equipment controls are in the proper operating position.
Train workers to perform the LOTO process.
Apply appropriate tags both locally and remotely.
Confirm the device is de-energized by proving it will not run when started.
Confirm all unnecessary items have been removed from the area.
Question: 88
Which two of the following are means in which radiated interference primarily enters electronic devices? (Select two options.)
Proximity to interfering sources
Missing or inadequate optical connections
Missing or inadequate device or cable shielding
Interface designs
Input signal lines
Question: 89
For the MAXIMUM flexibility of a cabling system in a hierarchical star topology, ALL backbone cables and links to FR’s should be terminated at the
HC (FD).
IC (BD).
TR
MC (CD)
Which of the following statements Is CORRECT concerning best practice for horizontal cable management panels?
One RU of management panel for each RU of cable patch panel plus one additional RU of cable management
Two RU of cable management panel for each RU of patch panel
Three RU of cable management panel for each RU of patch panel
Two RUs of management panel for each RU of cable patch panel plus two additional RUs of cable management
Question: 91
Close out documentation is initially discussed in which of the following meetings?
Prime Contractor and Subcontractor Meetings
Kickoff Meeting
Weekly Progress Meetings
Vendor Meeting
Question: 92
Which two of the following are ADVANTAGES of underground conduit systems? (Select two options.)
Provide additional physical cable protection
Not adaptable for future facility placement or removal without disturbing the property
Economical over a long life
Require more installation time than aerial or direct-buried installations
Route planning is not as critical as aerial or direct-burial
Question: 93
What is the MAXIMUM recommended length for A in the image below?
70 m (230 ft)
90 m (295 ft)
C. 100 m (320 ft)
D. 150 m (495 ft)
E. 300 m (985 ft)
Question: 94
Which of the following is TRUE about convenience receptacles?
They are duplex or quad receptacles mounted on perimeter walls.
They must be powered by emergency power to prevent loss of service.
They shall be connected to occupancy sensors to ensure user safety.
They increase the count of outlets needed on the equipment racks.
They are those into which equipment, such as switches, shall be plugged
Question: 95
When designing a video communications network, which type of video communication link is two-person videoconferencing?
Point-to-multipoint bidirectional
Point-to-multipoint unidirectional
Unidirectional
PTP unidirectional
PTP bidirectional
Question: 96
The type of apparatus housed in TRs varies greatly in size, purpose and function. Which two of the following active equipment is included? (Select two options.)
Cross-connect facilities
Telecommunication’s equipment
Environmental controls
Lighting controls
Building system equipment
Question: 97
What is the MINIMUM fire rating for telecommunications spaces walls and wall linings, if not specified otherwise by local Authority Having Jurisdiction (AHJ)?
One hour
Two hours
Three hours
No minimum requirement
Question: 98
For optical fiber cabling, which of the following test instruments is used to locate and identify any anomalies?
OTDR
Optical power meter
OLTS
Spectrum analyzer
Question: 99
What is the OPTIMAL lime in the construction process for ICT submittals to be reviewed by the ICT distribution designer?
After the contract is awarded and before project close out
As part of the contract bid process to prevent project delays
Before the contract is awarded
At the beginning of the close out process
For a cost estimate, an ICT distribution designer should produce a document listing each task with a cost placed beside them. The type of document used is a
A. So
spare ad sheet
worksheet
database