PRF Dumps PRF Braindumps PRF Real Questions PRF Practice Test PRF Actual Questions Prince2 PRF Prince2 Foundation https://killexams.com/pass4sure/exam-detail/PRF QUESTION: 226 Identify the missing words in the following sentence. Configuration management typically includes [ ? ] as one of the five core activities. A. exception planning B. risk assessment C. stakeholder engagement D. status accounting Answer: D QUESTION: 227 Which is performed as part of the recommended risk management procedure? A. Allocation of a budget to investigate issues facing the project B. Review of risk management practices to ensure that they are performed effectively C. Sending of information about risks to the project to project stakeholders D. Resolution of conflicts between the project and the programme board Answer: C QUESTION: 228 Which theme addresses the need to have a strategy for communicating with stakeholders? A. Quality B. Organization C. Plans D. Progress Answer: B QUESTION: 229 Which project characteristic suggests that projects should have a defined start and a defined end? A. Change B. Temporary C. Cross-functional D. Risk Answer: B QUESTION: 230 Identify the missing word in the following sentence. The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment. A. activities B. processes C. products D. quality Answer: B QUESTION: 231 Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete? A. Executive B. Senior User C. Senior Supplier D. Project Manager Answer: B QUESTION: 232 Which is a true statement about time-driven controls? A. Time-driven controls are used for monitoring the progress of Work Packages and management stages B. Time-driven controls take place when specific events happen C. Time-driven controls are produced at the end of a stage D. An Exception Report is a time-driven control Answer: A QUESTION: 233 What theme defines and implements the means by which the project will verify that products meet business requirements? A. Business Case B. Change C. Progress D. Quality Answer: D QUESTION: 234 Which is a Benefits Review Plan used to assess? A. How the project's products have performed when in operational use B. The effectiveness of the project strategies C. The progress of the project against its plans D. The suitability of the project management team structure and membership Answer: A QUESTION: 235 What needs to be in place to ensure effective issue and change control? A. Configuration management system B. Manage by exception C. Quality planning D. Information needs for stakeholders Answer: A QUESTION: 236 Which is a purpose of the Initiating a Project process? A. Decide if it is worthwhile to initiate a project B. Decide on the project approach C. Establish solid foundations for a project D. Identify the number of Work Packages required Answer: C QUESTION: 237 Why does PRINCE2 recommend three different levels of plans? A. To cover initiation, specialist work and exception situations B. To provide appropriate detail to each of the different levels of management within the project C. As an allowance for initiation, product delivery and project closure D. To match the different aspects of the product-based planning technique Answer: B QUESTION: 238 What theme provides the justification for the project? A. Quality B. Plans C. Progress D. Business Case Answer: D QUESTION: 239 Which product records any project outcomes perceived as negative by stakeholders? A. Business Case B. Project Plan C. Communication Management Strategy D. Project Product Description Answer: A QUESTION: 240 Which product is used by the Project Manager to authorize work? A. Team Plan B. Stage Plan C. Work Package D. Product Description Answer: C QUESTION: 241 What do customer's quality expectations identify? A. Standards that must be used in order to meet the level of quality needed B. Skills required to develop the project product C. Measurable definitions of the attributes required for a set of products to be acceptable to the customer D. Reviewer names for each product Answer: A QUESTION: 242 Who does the Team Manager report to and take direction from? A. Project Board B. Project Assurance C. Project Manager D. Project Support Answer: C QUESTION: 243 Identify the missing words in the following sentence. The [ ? ] should include representation to satisfy the interests of the three primary categories of stakeholders affected by a PRINCE2 project. A. Corporate or programme management B. Project Board C. Team Managers D. Project Support Answer: B QUESTION: 244 What is described as an organization's unique attitude towards risk taking? A. Risk appetite B. Risk management C. Risk evaluation D. Risk tolerance Answer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